Phase 1- Track and Field Project
The Greene County Board of Education held a called meeting, Thursday April 10, 2025 to consider a bid for athletic improvements to Greene County High School – Phase I – GCHS Track and Field Project. Superintendent Dr. Corey Jones stated that the purpose of the meeting was to lock in material and other costs for the Project in light of current US economic conditions.
He explained that the two initial bids from Game Day, Inc at $2,244,444 and J.T. Harrison at $1,899,000 were both over budget, therefore there was a re-bid with only Game Day Inc. proposing a cost of $1,683,748.
CSFO Mrs. Marquita Lennon, displayed the category of funds available for the Phase I Track and Field Project at GCHS: FY 2024 K12 Capital Grant – $1,100,000; FY 2025 K-12 Capital Grant $84,615.38; Fy 2024 Education Trust fund Advancement and Technology Fund – $111,900; FY 2025 Education Trust Fund Advancement and Technology Fund (Proposed) $575,000. These fund categories total $1,871,515.38.
The board members questioned the difference between Game Day Inc.’s initial bid and the second re-bid. Dr. Jones and CSFO Lennon explained that changes and/or substitutions to the plans and specifications were reflected in the re-bid.
Although Superintendent Jones was able to reach the Architectural Firm of McKee & Associates during the board meeting and the board was able to make inquiries at the time concerning deletions to the original Project Specs, they seemingly were not satisfied and requested an in-person meeting with Walter McKee at the next board meeting. No further action was taken on the GCHS Phase I -Track and Field Project.
On the superintendent’s recommendation, the board did approve the quote of $27,570.62 from AngelTrax to upgrade camera/surveillance system and add windshield cameras on school buses.